Eighteen months ago, Vera Bradley Co. was planning a major move to a new manufacturing and distribution center. Here’s an update—with some lessons learned.
While it’s tempting to make comparisons
between current and former material handling
systems, this is one instance where
comparisons don’t—well, compare. “You
can’t really compare this to what we had on
Progress Road [site of the company’s old
distribution center],” says Larry Harness,
distribution manager, “because now it’s
like a whole new business.”
He’s right. Even before the company moved into its new location southwest
of Fort Wayne, Ind., in February, business had been growing faster
than anticipated—the good news. Keeping up with, or ahead of, that growth
has been the challenge—to say nothing of adapting to all-new handling systems,
processes and equipment in a special environment.
“It was a huge bite we took, moving out here,” explains Harness. “However,
in business today, given its fast pace, there’s bound to be some pain, so you
just work through
ADVERTISEMENT
|
it.”
Vera Bradley opted to take its pain in one quick dose rather than spread
the inconvenience of moving over a protracted period. Harness says everyone
in the company just agreed: Let’s get the job done. “If you do it in small
increments, you just get the same pain over and over,” he says with a laugh.
Harness and other managers talked with many companies as they planned
their move. The conclusion was that there were few choices. Just do it.
Lessons Learned
Asked what he could have used
to make a smoother transition going
from multiple locations into a single,
new facility, Harness doesn’t hesitate
to say, “The thing we needed most
was a 40-hour day! There was just
not enough time. Our inventory was
huge, and moving it from many locations
into here…Well, we didn’t
have enough dock doors to get it all
in on schedule.”
 |
|
The expanded sewing, amidst bolts of material in the area of the distribution center, is used
for value-added processes.
|
Populating the system with inventory
is a challenge because you can’t
stop production. In retrospect, he
adds, be more realistic about the
goals you establish. You shouldn’t be
too aggressive when migrating to a
complex system. “We did our benchmarking
and based our numbers on
businesses that were not as complex
as ours,” says Harness.
And, while they might have come
up short on some of the numbers,
in the end—or the beginning, actually—
Vera Bradley has a good, solid
system. “Since we were installing the
SAP system, there was no reason
not to do the WMS piece, too,” says
Harness. It opted to use Manhattan
Associates for managing its inventory
movements. To keep product
flowing, it installed a Dematic C-L
conveyor and sortation system. Also
new to this location is the very-narrow-
aisle rack scheme, featuring turret
trucks from Raymond. The planning,
design and system integration
was done by Forte Industries.
Along with more time, Harness
would like more space. “It’s never
big enough, is it?” he asks rhetorically.
“We asked for a five-year
building; however, business has been
good, so, even though we’ve been in
only 10 months, we’re already into
the second phase of our pick module
plan.”
That plan will add a third tier to
the current two it uses. The automation,
usually thought of as somewhat inflexible, is appropriately flexible,
says Harness. The original plans
called for putting in the infrastructure
for growth; it’s just that the growth
spurt happened a bit sooner than anticipated.
Back to the Future
 |
 |
|
Cramped conditions of the former distribution center have been eliminated with a central takeaway conveyor and work conveyors along both pick faces.
|
Less than two years ago, distribution
(and some manufacturing)
for Vera Bradley was located in an
industrial park on Progress Road,
just down the street from the corner of Profit and Dividend. If you’re superstitious
about your business, that
would be a tough address to leave. It’s
gone well, however, for this manufacturer
of woman’s exclusive handbags
and accessories. And, it produces
them by the millions—4.5 million in
2005, for example.
“Our year-on-year growth over the
past five years has been in the range of
20% to 30%,” said Matt Wojewuczki,
vice president of operations, at the
time of our first interview. Those
numbers have held up for the past
couple of years.
Barbara Backgaard and Patricia
Miller began their business with a
strong friendship and a great idea.
From a basement, to a garage, to multiple
buildings, growth has been the
hallmark of this company. Now, more
than a quarter of a century later, the
Vera Bradley Co. is in the midst of expanding its 70-acre campus. The
new, 200,000-square-foot distribution
center is just the beginning of this
manufacturer’s campus. An administration
building is planned, along with
a value-added manufacturing plant,
a welcome center and a retail store.
There will be ponds, guest walkways
and, eventually, gardens.
If, as Harness says, it’s not possible
to compare the business of 2005 with
the business of 2007, it is possible to
compare the facilities and methods of
handling. Walking through the new
building, it’s easy to see how the earlier
education in, and commitment to,
a 5S methodology is paying off. This
tactic of organizing the workplace for
safety, cleanliness and ergonomics
within the framework of lean manufacturing
is reflected in the sparkling
floors and debris-free aisles.
In the receiving area, truckloads
(about four per week) of rolls of
quilted material and other supplies
arrive in cartons. Barcode labels direct
movement of pallet loads to endof-
aisle pick-up and drop positions.
Operators scan the labels for rack
locations in the multi-aisle, high-bay
storage areas. Two aisles in the rack
system are dedicated to raw material
storage.
All of the creative work for the Vera
Bradley designs is still done in Fort
Wayne. Fabric, imported from Asia
and quilted in Kansas City, is cut into
kits in this new facility. An expanded
sewing area in the new building allows
for more value-added operations.
Kits of products are cut with computer-
aided machines, then parsed
out to five local sewing companies:
three in Indiana and two in nearby
Ohio.
Finished product is returned to
the distribution center from the sewing
companies in corrugated cartons.
These cartons are moved into picking
slots during replenishment.
“One of the challenges we still
have,” says Harness, “is the balance
between pallet flow and carton flow.”
Depending on the time of year, pallet
loads of goods are coming and going within the racks. As the seasonal business
tapers off, only cartons of material
are moving. “We try to consolidate
the cartons [in the slotting scheme] to
reduce the amount of walking order
pickers have to do.”
Finding the ideal slotting program
is the same challenge Harness had
in the old facility because of the nature
of the business. “In the fashion
industry, we have major releases of
new items twice a year,” he explains.
“So, we have to build up the inventory
of finished goods, then release them to all the stores at the same
time.”
And, six months later, what was
fashionable—and an A mover in the
warehouse—is relegated to being a B
mover that has to be removed from
the order selector’s golden zone.
During the slower months, the distribution
center moves about 30,000
items per day. At the time of a new
product release, that number soars
to more than 100,000 items per day.
Order Fulfillment
 |
|
Putaway cartons are scanned
and moved into rack locations.
|
Order selection is done in waves
established through the SAP and
WMS software. All the information
the order picker needs is contained
in the printed barcode labels as well
as printed on the label. When the
label is scanned at the beginning of
the process, the operator initiates all
order directives, including which of
a half dozen cartons or envelopes
to use for shipping the order. As
the carton moves along the line, the
operator scans the label to initiate
picking locations in the pick-to-light
modules. Cartons can be diverted
along the line, if necessary, via popup
wheels. If a carton is not diverted
from the central takeaway conveyor,
in the case of completed orders, it travels up and over the order selection area to the
sortation system. Here, cartons are sorted, via barcode
label information, then diverted to loading
areas designated to specific carriers. Air-pillow dunnage
is used to fill cartons before they pass through a
semi-automatic carton taping machine and into trailers.
“Occasionally, we send a carton off to the audit
area,” explains Harness. “It can be a random audit
check for weight tolerance or to get a packing list.”
Harness says acceptance of the equipment and
processes by employees was not much of a challenge.
Lift truck operators had to be certified, for example.
“It’s tough to simulate doing these things for employees,”
he says, “so we had classes, and everyone
learned how to operate the equipment at the same
time.”
Asked where the next big challenge lies, Harness
looks toward the back of the building where employees
are opening cartons and sorting product
by hand. “It’s in returns and how to handle them,”
he says.
Sounds like we’ll be coming back in the future.
|