Project management can best be done by a third party
When you're responsible for distribut -ing dreams--hundreds of thousands of dreams--you want to be sure you
do it right. That's the day-to-day
business of David's Bridal. This national retailer of virtually everything to do with weddings (You add your own potential spouse.) currently
supplies 275 retail outlets from its two distribution
centers in eastern Pennsylvania. The newer center
is located in Bristol, just north of Philadelphia. Its unpretentious building houses more than 150,000
square feet of everything the bride and her brides
maids need--from shoes to tiaras, ribbons to cake
cutters.
About three years ago, Tony Coccerino Jr., direc
tor of operations, and other company managers,
knew their business was at a crossroads. It needed a
guide to point them in the right direction. The guide
turned out to be Bryan Jensen, vice president, St.
Onge Co., York, Pa.
When to ask for help
Jensen metaphorically describes when
ADVERTISEMENT
|
a company
should seek out a project manager, or third-party assis
tance: You don't call a lawyer if you don't need a lawyer.
And when you do need a lawyer, you don't rush off to law
school to begin studying.
"The same applies to material handling," he says. "Our
business is to bring to the client a level of expertise he
either does not have available when looking at technical aspects of a system, or does not have time to dedicate to
project management."
The latter was the case with David's Bridal and Tony
Coccerino. "I have a business to run," says Coccerino.
"We looked at the potential growth in our business and assigned a network analysis team to review the options."
That's when they turned to the experts from St. Onge
who began working on a master plan—Phase I.
He adds that the plan Jensen and his team developed
far exceeded what he, Coccerino, had imagined. "It essentially changed the way we do business. In the end, we were
able to cut about a day and a half from our time to market
and reduce costs all along the line." That's the kind of help
people look for when they hire a project manager.
Jensen says, while most projects follow similar paths, no
two are alike. Phase I, or the design phase, is alternative
driven. "Any insight [for how it does business] you bring
to the client," says Jensen, "has to improve upon what
they are already doing, especially if they're already doing
it well."
In this case, the big idea from Phase I was essentially to split the company's business into two parts. Its existing
facility, in Conshohocken, was distributing garments on
hangers (GOH) as well as flats, or merchandise in cartons. The optimal design called for converting the Conshohocken operations to distribute GOH exclusively and
start a new facility for distribution of ˚ats. With the major
hurdle of what to do cleared, Jensen and his team, which
varied in number, depending on the phase of the project,
helped the client with the next step—identify Bristol as the
right location for this new part of the business.
Phase I
There are plenty of ways to distribute cartons from a
distribution center to retail stores. " In this instance, we gave
the client four options for distributing its product," says
Jensen. "Because those options are alternative driven, it [the client] can see the impact if it puts less
money here, it will have to put more
money there. These are all values—the
realities of going for the longer time
for payback versus instant gratification, for example."
Jensen says clients also have certain
predispositions toward a brand or technology, so having alternatives based on
data—hard values—helps to take any
"emotion" out of the equation.
And, getting the data to generate
those alternatives is not always the
easiest of tasks, he says. "Most companies have the information we need
to create the scenarios; the challenge
comes in extracting the data."
Typically, companies are collecting a lot of information related to
SKUs but not enough about dimensions and weights. More often than
not, the critical factor in determining
the core part of a material handling
system will depend on the size of the
units to be moved.
To get all the right numbers, Jensen and his team spent a lot of hours
on the floor at the existing facility in
Conshohocken. They watched what
employees did and asked why it was
done that way. "You have to learn the
process," says Jensen, "because you don't want to design a plan that precludes them from doing their job as it
exists now if they're efficient at it."
Knowing the client's business well
forms the basis for the alternatives
presented. Jensen likes to say the St.
Onge team designs for equipment
robust enough that will allow the client to serve its peak operating points,
and be cost effiective at average running speeds. Knowing the client's
business well forms the basis for the
alternatives presented.
A project is not designed and managed for what is; it's all about what
will be. Jensen and his team spent
time with David's Bridal's procurement managers to discuss packaging
alternatives and learn of any changes
that might occur before the new system was installed. David's was in the
process of upgrading its WMS, so
that had to be another facet added
to the mix, mostly in the category of
"what to watch for".
Finally, the project management
team spent time with the compa
ny's vendors to learn how product
is shipped. Knowing how it will ar
rive at the new facility determines
whether changes that might enhance
the project can be initiated from the
supplier's end.
Phase II
The second phase of the project,
after about 12 weeks of design work,
is preparing for and sending out re
quests for proposals (RFPs). At this
point, details are paramount. So that
all bids are created equally, even the
most minute things have to be de
~ned in the RFP, says Jensen. In this
situation, three RFPs were prepared:
One covering conveyors and sorta
tion, one for storage media, and a
third for mobile equipment.
Depending on the level of client in
volvement, typically the project man
ager becomes a negotiator or serves
as an agent for its client. "The team
from St. Onge set up meetings with
potential vendors who then came in
or took us on visits to existing facili
ties," says Coccerino.
Getting a project manager involved
in the vendor selection process can add
some weight for smaller businesses.
Typically, larger equipment vendors
are slow to respond to requests from
small companies, says Jensen.
In addition, because the project
manager is more familiar with state-of-the-art equipment, it can steer the
client toward better options, more
reliable vendors or alternative costs.
"We take an engineered labor
standards approach to evaluate head
count involvement for each level of
the task at hand," says Jensen, "so the
headcount versus capital investment
comparisons can be made."
Phase III
After the client has signed on
the equipment vendors, the project
manager's role shifts a bit from be
ing an adviser to an overseer. In this
case, the St. Onge team, which varied
from three to five people, depending
on complexity of the tasks at hand,
found the architect to complete the
"white space," or internal configuration, of the shell David's was leasing.
"When the equipment starts show
ing up," says Jensen, "we know the
order of installation. We're here to
ensure all targets are being hit. Some
clients prefer to run the whole pro
cess through its general contractor;
others like to do it themselves."
In any case, the project manager
has to be there to check the instal
lation of equipment against the en
gineered drawings and, during the
commissioning of equipment, to
make sure everything is as specified.
The ultimate test is going live. Coc
cerino says the smoothness of the
transition of processing orders in two
locations was nearly transparent to
its retail stores. Product was moved
from the old location to the new dis
tribution centers in batches of styles.
This was done mostly on weekends.
"When an order came in for a par
ticular style," he says, "we could shunt
that part of the order to whichever
location had the item and fulfill all
parts of the order at the same time.
Most stores never knew we had made
the switch." Because everything is
shipped via small parcel carrier, there
was no freight penalty for shipping
split orders.
The end result of the project is an
installation that blends very-arrow-aisle rack layout, man-aboard order
picking trucks, a bomb bay-style sor
tation system and the efficient use of
automatic data collection.
How it works
As cartons of merchandise enter
the distribution center, vendor-ap
plied UPC labels are scanned and
pallet loads built in the receiving area.
The warehouse management system
assigns a lift truck operator to the
putaway task of moving those pallets.
The lift truck operator scans a carton
label, and the WMS tells him, within
three aisles either to the right or left
of his current location, where to put
the pallet. Items are matched to the
rack location. Two or three cartons are
placed in each location in the racks.
When tasked to fill an order, op
erators receive the item's location and
full cartons are retrieved from the
racks and taken to the packing station.
There, an operator picks the number
of items required to fulfill the order,
scanning each as it is removed from
the original carton and placed in a
second carton that will move via conveyor to the sortation area.
"We use the vendor's original car
tons for storage," says Coccerino,
"sending merchandise to the sorter
and for sending partial carton loads
back into storage."
If the order calls for a full carton,
the order picker bypasses the pack
ing station with the carton and puts it
onto the conveyor destined for ship
ping workstations. The WMS does
all the decrementing of merchandise.
Coccerino gets a lot of reuse from his
corrugated cartons because he has
given his vendors specifications for
size and durability. "Our conveyor is not all that long or damaging," he says,
"but we make sure we get cartons that
will hold up in the system".
The company has also specified its
shipping cartons to be durable to with
stand the rigors of the UPS sortation
process. Boxes are made with overlap
ping tops to prevent damage to mer
chandise when opened at the retail lo
cations. Interlocking bottoms on the
cartons reduce the amount of tape
needed to close them, and they ride the
conveyor better.
High-speed sorting
The bomb bay, or bottom-drop sorter, is 242 feet long and diverts merchandise to 204 destinations. Chutes were designed so that orders for as many as 600 stores can be sorted simultaneously. Employees at four manual induction areas place items received from packing station cartons onto one of the trays. The merchandise passes
through a scanner array and down the proper chute.
Of the many sortation options available, this one fulfilled the requirements of the system
best, says Coccerino. "The placement
of the EuroSort solution gave us more
room within the chutes to accumulate
product, and it's simple to operate in
terms of minimal maintenance. There's
essentially no lubrication required and
no air to drive any of the mechanical
parts. It's also quiet running," he says.
Jensen, one thing about this project
that made it difierent from others was
the fact that his team was not creating
a facility for expansion. "The big decision was essentially to split the existing
business, consequently we were man
aging for new ways of operating as well
as finding ways to add efficiencies."
Bringing in outside help in the form
of a project manager o˚ers several
benefits: Expertise hired for only the
period of time needed; continuity from
design through going live is ensured;
and flawless execution of the project is more than likely
because the project manager is not distracted by other
day-to-day requirements of his job.
For more information
contact any of the
participating vendors in the
David's Bridal distribution
center project:
- St. Onge Company, www.stonge.com;
- Century Conveyor, conveyor, www.centuryconveyor.com;
- EuroSort, sorter, www.eurosort.com;
- Steel King, racking, www.steelking.com;
- Raymond, very narrow aisle lift
trucks, www.raymondcorp.com;
- Manhattan Associates,
warehouse management system, www.manh.com;
- 3M, carton sealers, www.3m.com;
- Arbor Material Handling, lift
trucks, www.arbor-inc.com.

The overhead bomb bay-style sorter has
more than 200 trays and can sort to as
many as 600 locations.

Very-narrow-aisle order picking is used
to pull full cartons that are sent to the
packing stations. Partial cartons are
returned to the racks.

Bryan Jensen (left) and Tony Coccerino
worked together to create a new way of
doing business at David's Bridal Company.
|